What Are ICRA Compliant Containment Walls? A Guide for Healthcare Contractors

A wall is never ICRA compliant on its own. Here is what ICRA 2.0 asks of a containment wall, how your class gets set, and where installs fail inspection.

Construction Containment Services (5DCCS) Healthcare and ICRA Updated November 2026

ICRA compliant containment walls in a hospital hallway, with two professionals in business attire and a staff member in scrubs walking past a temporary modular wall.

Picture the walkthrough. The containment wall is up and the panels look clean, and the infection preventionist still stops the project, because the barrier ends at the ceiling grid and nobody planned the seams. Nothing was wrong with the panels. The setup around them was never matched to the project's ICRA class.

That is the risk hiding behind the phrase "ICRA compliant containment walls." ICRA is not a product certification. It is an infection control risk assessment completed for each project, and it decides what the whole containment setup has to deliver. The wall is one part of that setup.

When a manufacturer says a panel exceeds a given ICRA class, that describes the panel. It does not describe your corridor, your ceiling, or your project.

This guide is for contractors who are new to healthcare containment or tired of failed walkthroughs. It explains what ICRA compliance means for a wall, how the class for your project is set, what a wall has to do, and how to choose one.

What ICRA Compliance Means for a Containment Wall

ICRA stands for Infection Control Risk Assessment. Hospitals and clinics use it to judge the infection risk of construction, renovation, or maintenance work before it starts, and to decide which precautions the work must follow. The American Society for Health Care Engineering (ASHE) updated the original framework as ICRA 2.0, which HFM Magazine reported in October 2021. It added a fifth class of precautions, a formal look at the areas around the project, and clearer activity descriptions.

The assessment follows five steps: define the activity, identify the patient risk group, match the class of precautions, assess the surrounding areas, and set the mitigation plan. The class belongs to the project, and the facility's ICRA team and infection preventionist own it.

The class belongs to the project. The wall only helps you meet it.

ICRA compliant containment walls help you meet that class when they are installed to the right height, sealed at every seam, and paired with the air control your plan calls for. Without those pieces, even a well-built panel will not carry the project through inspection.

How the Matrix Sets Your Class of Precautions

Two inputs decide your class. The activity type (A through D) reflects how much dust and disruption the work creates. The patient risk group (Low, Medium, High, or Highest) reflects how vulnerable the people nearby are. The ASHE matrix combines them.

ICRA 2.0 class of precautions by risk group and activity type
Patient risk groupType AType BType CType D
LowClass IClass IIClass IIClass III*
MediumClass IClass IIClass III*Class IV
HighClass IClass IIIClass IVClass V
HighestClass IIIClass IVClass VClass V

Type A is inspection and other non-invasive work, Type B is small, short jobs with minimal dust, Type C is larger or longer work with moderate dust, and Type D is major demolition and construction. A multi-room renovation (Type D) next to patient rooms (High risk) lands at Class V. The same work beside a non-clinical office (Low risk) lands at Class III. That is why one wall system can be routine on one project and nowhere near enough on another.

Good to know. Per the ASHE tool, the asterisks mean the work should be raised to Class IV negative air requirements if the work area cannot be sealed off from occupied patient care space. An infection control permit and approval are required for Class III (Type C) and for all Class IV and V work. Your facility's own ICRA form is the document that governs your project.

The matrix above follows ASHE's ICRA 2.0 training materials. For a detailed look at how Class IV and Class V differ, including Bay Area and California requirements, read our guide to ICRA Class IV vs. Class V for Bay Area hospital containment.

What ICRA Compliant Containment Walls Have to Do

Whatever the class, ICRA compliant containment walls have the same basic job: keep the work zone separate from the occupied space, and stay that way until the area is cleaned and inspected. In practice, that means a wall that:

  • Forms a continuous, sealed barrier. It runs to the ceiling or, if ceiling tile is removed, to the deck above, and it is sealed at the floor and at adjoining walls.
  • Meets the fire requirements for the class. At Class IV, critical barriers must meet NFPA 241, so ask about fire performance early.
  • Has a cleanable, non-porous surface. Facilities want a barrier they can wipe down, especially near surgical and sterile areas.
  • Seals around penetrations. Pipes, conduit, cables, and ducts that pass through the barrier need sealing, and Class V calls this out for both the containment and anteroom barriers.
  • Controls the entry. Doors close and seal properly, and at higher classes the entry runs through an anteroom.
  • Works with air control. The panels need to hold a seal under the negative pressure and HEPA exhaust your plan specifies.
  • Comes down cleanly. Barriers stay in place until cleaning is complete, and removal should not create a second round of dust.

The picture below shows one way a wall misses the first item.

Section view comparing a wall that stops at the ceiling grid with a wall that runs to the deck On the left, a wall stops at the ceiling grid and air travels through the open plenum over the top. On the right, the wall runs to the deck above and is sealed at the deck and floor, so air stays on its own side. Stops at the ceiling grid Runs to the deck, sealed Open plenum Occupied side Work zone Air and dust travel over the top Plenum closed off Occupied side Work zone Air stays on its own side. Gold marks sealed joints.
Section view, not to scale. Your ICRA team sets the actual requirements for your project.

Wall Mistakes That Fail ICRA Inspections

These problems show up in the seams, not in the panels, and each one is easy to prevent at the planning stage.

  1. The barrier stops at the ceiling. A wall that ends at a suspended grid with an open plenum above it lets air travel over the top, as the picture shows.
  2. Gaps at the floor, ceiling, and wall junctions. Perimeter seams need a sealing method your facility approves. A small gap is enough to defeat a pressure differential.
  3. Unsealed penetrations. Anything that passes through the barrier needs sealing. Penetrations through fire-rated assemblies also need appropriate firestopping, so confirm requirements with your AHJ.
  4. A weak entry. Doors, mats, and the anteroom are where dust leaves on shoes, carts, and clothing.

For the consequences when dust does escape, see our guides on what happens when construction dust escapes the work zone and how to prevent construction dust in occupied spaces.

Modular Walls vs. Drywall vs. Plastic Sheeting

Any of the three can appear in an ICRA plan, depending on the class and the facility's policy. They differ most in the dust they create and how well they hold a seal.

How common barrier types compare for healthcare containment
BarrierDust at install and removalSurface and sealReuse
Plastic sheetingLow at install, but it can tear or billowFlexible, hard to keep airtight under pressure. Usually limited to short, lower-class workSingle use
DrywallHigh. Cutting, taping, sanding, and demolition create the dust you are trying to containRigid and can be sealed, but finishing takes timeSingle use, with debris to haul out
Modular wallsLow. Panels install and come down without cutting, taping, or sandingRigid, non-porous, and cleanable. Still depends on perimeter sealing and air controlReusable across projects

Ask about fire performance before you settle on a system. Rigid modular assemblies with a one-hour fire rating exist for projects that need one, and our guide to fire-rated temporary walls on jobsites explains when that matters. Confirm the requirement for your project with the facility and your AHJ.

How to Choose ICRA Compliant Containment Walls

Use this checklist before you order ICRA compliant containment walls or submit a containment plan.

  1. Get the project's class and permit in writing. Every other decision follows from the ICRA form your facility completes.
  2. Plan the height. Confirm whether the barrier must run to the deck and how it terminates at the structure above.
  3. Ask for documentation on the system. Request fire test data for the panels and, where a rated barrier is required, the one-hour fire rating report.
  4. Specify a non-porous, cleanable surface. Your infection preventionist will want to wipe it down.
  5. Detail the seams before install day. Floor, ceiling, wall junctions, door frames, and penetrations each need a sealing method.
  6. Coordinate with the air side. Confirm who supplies HEPA negative air and pressure monitoring, and that the walls hold up under them.
  7. Agree on inspection and removal. Know who inspects, when, and what must be cleaned before barriers come down.

At 5DCCS, we rent and sell modular wall systems for occupied healthcare work across Northern California. We can help match panel type, height, and perimeter details to the class your ICRA team assigns, and we are familiar with the local requirements that tend to come up. We do not set the class or approve the barrier. That decision stays with your infection preventionist, your facility, and your AHJ.

For project types we support, see our pages on healthcare containment and biotech and cleanroom containment. If you are comparing costs, our modular temporary wall pricing guide is a good starting point.

Frequently Asked Questions About ICRA Compliant Containment Walls

What does ICRA stand for?

ICRA stands for Infection Control Risk Assessment. It is the process healthcare facilities use to evaluate infection risk and set precautions before construction, renovation, or maintenance work begins.

Is there such a thing as an ICRA certified wall?

No wall earns an ICRA class by itself. ICRA is a project-level assessment, so compliance depends on how the wall is installed, sealed, and paired with air control. Some manufacturers describe panels as meeting a given class, which is useful documentation, but your infection preventionist confirms what your project requires.

What is the difference between ICRA Class IV and Class V?

Class V builds on Class IV with additional requirements, and the class your project lands in depends on the activity type and patient risk group. Our guide to ICRA Class IV vs. Class V for Bay Area hospital containment covers the engineering differences in detail.

Who approves the containment setup?

The facility's ICRA team, including the infection preventionist, owns the assessment. An infection control permit and approval are required for Class III (Type C) and all Class IV and V work, and an infection preventionist or designee and an engineering representative inspect the area before precautions are stepped down.

Can plastic sheeting be used for ICRA containment?

Plastic sheeting is usually limited to short-duration, lower-class work, and it is hard to keep airtight under negative pressure. Check your facility's policy before relying on it for Class IV or V, where rigid barriers are the more common choice.