📍 Headquartered in San Jose, CA and Servicing Northern California

Data Centers & Mission-Critical Facilities

Construction Containment for Live Data Centers That Cannot Go Down

Unplanned data center downtime costs as much as $9,000 per minute. Dust, debris, ESD contamination, and airflow disruption from construction are direct and preventable contributors to that number. 5DCCS provides modular containment systems engineered for mission-critical environments. Our walls are fast to install, debris-free at removal, and built to preserve the thermal and air quality conditions your equipment depends on.

ASTM E84 Class A Fire Rated ESD-Aware Installation Practices Negative Air / HEPA Compatible Zero Demolition Debris SDVOSB & DVBE Certified
$9K/min
Cost of Unplanned Downtime
54%
of Major Outages Exceed $100K
100V
ESD Damage Threshold for Semiconductors
PM2.5
Particle Size That Lodges Inside Equipment

One Containment Failure Can Cost More Than the Entire Project

Live data centers operate under environmental requirements that have no parallel in conventional commercial construction. Airflow, temperature, humidity, electrostatic charge, and physical contamination are all actively managed within fractions of an inch of water column pressure and within single degrees Celsius. A construction activity as routine as drilling into a wall or removing a raised floor tile releases particulate matter and debris that can migrate into server intake paths, settle on circuit boards, and cause failures that look like hardware problems but are actually contamination events.

Uptime Institute's research found that 54% of significant data center outages cost more than $100,000, with 16% exceeding $1 million. Unplanned downtime can reach $9,000 per minute for large enterprises. Inadequate construction containment is a direct and preventable contributor to those numbers. The cost of proper containment is trivial compared to the cost of a single contamination-driven outage.

Modular temporary containment wall in active data center server room

Dust, ESD, and Zinc Whiskers Are Not Hypothetical Risks

Construction generates gypsum dust, concrete particles, silica, metal fragments, and fine particulate matter. Particles as small as 2.5 microns which are smaller than what the human eye can see and lodge inside server enclosures and are difficult to dislodge without causing further damage. Electrically charged dust can cause signal disturbances, data loss, short circuits, and power failures. Dust blocking air vents forces cooling systems to work harder, increasing power consumption and shortening equipment lifetime.

Electrostatic discharge (ESD) is an even more insidious threat. Semiconductors can be damaged by discharge events at voltages as low as 100 volts — a threshold far below what workers can detect. Construction personnel moving across non-ESD flooring, using non-grounded tools, or contacting synthetic materials generate triboelectric charge that presents a real damage risk to live hardware. In raised-floor environments, disturbing floor tiles can also release zinc whiskers (microscopic conductive filaments that become airborne and cause intermittent short circuit failures when drawn into server hardware through cooling air paths).

Clean room and data center precision environment containment

Containment Solutions for Every Mission-Critical Environment

Every data center and controlled-environment facility has distinct uptime requirements, cooling configurations, and contamination sensitivities. Here is how we support active construction across the full range of mission-critical project types.

🖥️
Live White Space

Active Data Hall Renovations & Expansions

Upgrades to live server rooms — CRAC unit replacements, power distribution changes, raised-floor modifications, cable tray additions — require construction to happen while adjacent racks remain in production. Our barriers isolate the work zone from live equipment, seal raised-floor plenum access points, and prevent particulate migration through the hot-aisle and cold-aisle cooling path during the entire duration of work.

❄️
Thermal Integrity

HVAC & Cooling System Upgrades

Replacing or adding cooling infrastructure — CRAC units, in-row coolers, chilled water systems, or economizer upgrades — disrupts the airflow conditions that adjacent IT equipment depends on. Our containment systems maintain the thermal envelope around live equipment during HVAC work, preventing the temperature excursions that ASHRAE TC 9.9 guidelines warn against and that trigger thermal shutdown or accelerated hardware degradation.

ESD Control

Electrical & Power Infrastructure Work

Switchgear replacements, UPS upgrades, PDU installations, and generator tie-ins involve construction activity in or adjacent to the electrical infrastructure that supports live IT loads. Beyond fire and debris control, our systems help define a physical boundary for ESD-aware work protocols — containing construction personnel and their tools within a zone where grounding and anti-static practices are actively enforced.

🏗️
Phased Buildout

Hyperscale & Colocation Facility Expansions

Large-scale data center expansions that add new halls or power zones adjacent to live operations require containment that can be reconfigured as each phase completes. Our modular systems accommodate phased buildouts without demolishing and rebuilding barriers — critical when the construction boundary moves every few weeks as new capacity comes online and old space is decommissioned or repurposed.

🔬
Air Cleanliness

Cleanroom & Controlled Environment Modifications

ISO Class 7 and Class 8 environments used for data center operations, network operations centers, and high-availability computing require air cleanliness standards that standard construction practices immediately violate. Our barriers provide the physical separation required to maintain classified air quality in adjacent spaces while renovation proceeds, with HEPA negative air integration available for the most contamination-sensitive adjacencies.

🔒
Access Control

Security Perimeter & Access Control Projects

Physical security upgrades — biometric access control installations, mantrap construction, security camera systems, and perimeter hardening — often require construction within the secure perimeter of a live data center. Our barriers define the construction boundary while maintaining the access control integrity of surrounding areas, controlling contractor personnel movement without requiring the facility to suspend normal operations or relax its physical security posture.

The Framework Governing Construction in Live Data Centers

Data center construction sits at the intersection of fire protection, electrostatics, air quality, and IT operations — each governed by its own set of standards. ASHRAE TC 9.9 defines the thermal envelope within which IT equipment must operate. NFPA 75 and NFPA 76 govern fire protection for information technology equipment and telecommunications facilities. ASTM E84 establishes the minimum fire rating for any material used as a construction barrier inside a data center. Uptime Institute Tier Standards define the operational availability requirements that constrain how and when construction can happen in a certified facility.

Containment barriers are not passive infrastructure — they are active tools for maintaining compliance with these standards during construction. A temporary wall that violates the fire suppression volume calculation, allows particulate to migrate into live equipment, or disrupts the hot-aisle/cold-aisle thermal balance is not a containment solution. It is a liability. Our systems are specified to address all of these requirements, not just the visible ones.

ASHRAE TC 9.9 — Thermal Guidelines Defines the recommended inlet temperature range (18°C to 27°C) and the maximum rate of temperature change for data center equipment. Construction barriers must not disrupt the hot-aisle/cold-aisle separation that maintains these conditions adjacent to live equipment.
NFPA 75 & NFPA 76 — IT & Telecom Fire Protection Governs fire protection for information technology equipment rooms and telecommunications facilities. Temporary barriers that subdivide a protected zone can affect clean-agent suppression volume calculations — a pre-construction coordination item with the facility's fire protection engineer.
NFPA 241 — Construction Fire Safety Requires a written fire safety plan and designated fire protection program manager for construction in occupied facilities. Our systems are compatible with NFPA 241 documentation and support temporary fire alarm coverage requirements within construction enclosures.
ASTM E84 Class A — Fire Rating The minimum fire standard for containment panel materials in occupied buildings. All panels in our systems carry Class A ratings for both flame spread and smoke development. Standard plastic sheeting and untreated drywall do not meet this standard in data center applications.
ASTM F150 — ESD Flooring Establishes criteria for static-dissipative flooring that safely controls electrostatic charge accumulation. Any temporary flooring or floor protection materials deployed within the white space must account for ESD properties — not just slip resistance.
Uptime Institute Tier Standards Tier III and Tier IV certified facilities require concurrent maintainability — no single planned maintenance activity can cause any load to go down. Construction activities must be planned and executed within this constraint, with containment barriers that do not create single points of failure in power or cooling redundancy.

What Plastic Sheeting and Drywall Cannot Do in a Live Data Hall

The data center industry's own published guidance is explicit: never use standard drywall or plastic sheeting as the primary containment barrier in white space adjacencies. Both fail the performance requirements of the environment. Here is what modular walls provide that those alternatives cannot.

💨

No Construction Debris — No Particulate Source

Drywall installation and removal generates gypsum dust that becomes a contamination source for live equipment. Our modular systems install without cutting, sanding, or generating airborne dust. When the project ends, panels are removed — no demolition debris, no dust cloud during teardown. The work zone closes without creating a secondary contamination event.

🌡️

Maintains Hot-Aisle / Cold-Aisle Thermal Separation

Plastic sheeting tears and gaps under positive and negative air pressure, disrupting the differential pressure balance between hot aisles and cold aisles. Our rigid panel systems maintain their seals throughout the project duration, preserving the airflow dynamics that keep server inlet temperatures within ASHRAE TC 9.9 recommended ranges for adjacent live equipment.

🔌

HEPA Negative Air Integration for Critical Adjacencies

When the construction zone is immediately adjacent to live server rows, negative air pressure inside the containment enclosure prevents particulate from migrating into the hot-aisle return path. Our panels accept HEPA-filtered negative air machine connections through sealed ports, creating the pressure differential required to stop contamination at the source.

Supports ESD-Aware Work Zone Protocols

The physical barrier is the first layer of ESD risk management. By clearly defining the boundary of the construction zone, our systems support the enforcement of ESD protocols for all personnel and equipment entering the white space adjacency. The barrier is where grounding verification, ESD wrist strap checks, and tool inspections happen before access is granted.

🔥

ASTM E84 Class A — Required for All Data Center Applications

Data centers typically operate under clean-agent fire suppression systems calibrated to the protected volume. A barrier material that burns modifies the fire dynamics the suppression system was designed for. Every panel in our systems carries an ASTM E84 Class A fire rating — the standard required for construction barriers in occupied facilities with mission-critical fire suppression systems.

🔄

Reconfigurable as Phases Advance Without Downtime Events

Phased data center expansions require the construction boundary to shift as each zone comes online. Tearing down and rebuilding drywall between phases generates debris and takes time — both of which create risk in a live environment. Our modular systems reconfigure quickly and cleanly, keeping the construction footprint controlled and the exposure window to adjacent live equipment as short as possible.

From First Call to Final Removal in 5 Steps

We make containment straightforward. Most setups complete in a single day, with no mess left behind on either side of the wall.

1

Consultation & Site Assessment

We review your scope, timeline, and compliance needs from drawings or a site walk.

2

Custom Containment Plan

We design a layout with door placement, negative air ports if needed, and multi-phase sequencing.

3

Delivery & Installation

Our crew delivers and installs. Most setups finish in a single day. Clean and professional on both sides.

4

Ongoing Support & Adjustment

Projects change. If your layout needs to shift or expand, we handle it without rebuilding from scratch.

5

Removal & Closeout

When work is done, we remove everything. No demolition dust, no debris, no cleanup left for your team.

Planning Construction in a Live Data Center?

Most quote requests receive a response within one business day. Tell us your facility type, your uptime requirements, and your construction scope, and we will put together a containment plan that protects your equipment and your SLA.

SDVOSB Certified DVBE Certified SBE Certified LBE Certified

Data Center Containment Questions

Not finding what you need? Call us at (855) 684-3752 or use the contact form — we are happy to talk through your project before you commit to anything.

No. Our modular panel systems install without cutting, drilling, sanding, or any process that generates airborne particulate. Panels connect to floor tracks and ceiling attachments using mechanical fasteners — there is no wet work, no adhesive, and no demolition debris during installation. This is one of the primary advantages over drywall in live data center environments, where even a small dust event during installation can create contamination risk for adjacent equipment.
Yes. Our panel systems include sealed ports for HEPA-filtered negative air machines. Maintaining negative pressure inside the construction enclosure prevents particulate from migrating into the hot-aisle return air path and from there into live server cooling systems. For construction immediately adjacent to live server rows, negative pressure containment is the recommended configuration — and our systems are designed to support it from the initial layout design.
ESD risk management in a data center starts before any panel goes up. Our installation teams understand that the damage threshold for semiconductors is as low as 100 volts — far below what a person can feel. We avoid synthetic materials, non-grounded tools, and non-ESD-compliant footwear within the white space boundary. Our panel materials are non-conductive and do not generate triboelectric charge. For projects where the data center operations team has specific ESD protocols, we review and comply with those requirements as part of the project setup process.
Zinc whiskers are a real and documented risk in older raised-floor data centers. These microscopic conductive filaments grow on zinc-electroplated floor tile undersides and become airborne when tiles are disturbed, traveling through cooling air paths into server hardware where they can cause intermittent short-circuit failures. For projects involving raised-floor tile removal, we work with the data center operations team to implement isolation containment before any floor tiles are disturbed, and we coordinate the HEPA vacuum protocols for plenum spaces and reinstalled tile undersides that best practice requires.
Properly designed containment should not disrupt hot-aisle/cold-aisle dynamics — and if it does, that is a design failure. We review the cooling layout and airflow path before designing the barrier configuration to make sure the barrier placement does not create hot spots at server inlets, block return air, or interfere with CRAC unit performance. For projects with complex cooling configurations, we involve the facility's data center engineer in the layout review before installation begins.
Yes. Tier III and Tier IV certified facilities require that any planned work go through a formal Method of Procedure (MOP) and change management process before execution. We can provide the technical information needed for your MOP documentation — panel specifications, fire ratings, negative air configuration, thermal impact assessment, and timeline — so your change management team has what it needs to review and approve the containment installation before work begins.
Our panels carry an ASTM E84 Class A fire rating for both flame spread and smoke development. However, any temporary barrier that subdivides a zone protected by a clean-agent suppression system can affect the suppression volume calculation — a pre-construction coordination item that requires review by the facility's fire protection engineer, not just the containment contractor. We flag this coordination requirement during project planning and can provide panel specifications to the fire protection engineer for their review.
Yes. Full-service rentals include delivery, installation, reconfiguration as phases advance, and clean removal at closeout. Self-service rental is available for organizations with in-house installation capability. System purchase is worth evaluating for data center operators or GCs with recurring mission-critical construction programs — the per-project economics shift significantly once you own the inventory. We can walk through the rent-vs-buy decision based on your projected project volume and frequency.